The exterior brick, stone, and glass is being installed.
The roof and exterior walls are being assembled.
The steel frame of the building is going up.
The foundation for the building is being poured.
The bunker that will become the recording studio is now visible.
Cement is being poured for the foundation.
The first layer of the parking lot is installed, allowing for more work to progress in a mud-free environment.
The retaining walls are finished, and the curb and gutter go in.
Retaining walls are being built, and stormwater pipes and pond are being installed.
Workers begin leveling the land and preparing the site for the building, driveway, and parking lot.
Workers begin leveling the land and preparing the site for the building, driveway, and parking lot.
Construction begins with the official survey and the removal of trees.
Stephen signs a contract with the builder.
The project is announced at a donor banquet. The Town of Clayton votes to rezone the property.
Wisdom purchases 1.25 acres of undeveloped land in Clayton, North Carolina. Work begins on plans and an artist rendering.